Beginning Tuesday, May 13, there will be detours for Spring Garden Ranch Road. The closure, located on the west end of Spring Garden Ranch Road, is needed for roadway resurfacing and to begin transitioning into work on the second half of the roundabout included in this project. No driveways will be impacted by this closure.
The planned detour routes are as follows:
- Motorists traveling east on Spring Garden Ranch Road wishing to travel to U.S. 17 will turn right on Argon Avenue, turn right on E Baxter Street, and then turn right onto U.S. 17.
- Motorists traveling south on U.S. 17 wishing to travel to Spring Garden Ranch Road will turn left on E Baxter Street, turn left on Argon Avenue, and then turn left onto Spring Garden Ranch Road.
- Motorists traveling north on U.S. 17 wishing to travel to Spring Garden Ranch Road will turn left on Spring Garden Avenue, turn left on Ponce De Leon Boulevard, turn left on E Baxter Street, turn left on Argon Avenue, and then turn left onto Spring Garden Ranch Road.
- Motorists traveling east on Spring Garden Avenue wishing to travel to Spring Garden Ranch Road will turn right on U.S. 17, turn left on E Baxter Street, turn left on Argon Avenue, and then turn left onto Spring Garden Ranch Road.
- Motorists traveling south on Ponce De Leon Boulevard wishing to travel to Spring Garden Ranch Road will turn left on East Baxter Street, turn left on Argon Avenue, and then turn left onto Spring Garden Ranch Road.
Volusia County Lane Closures
-
Motorists are advised that construction activities are underway along the southbound lanes of Ocean Shore Boulevard between East Granada Boulevard and Standish Drive. This work requires temporary lane closures and detours to safely accommodate drainage improvements, curb and gutter installation, and pedestrian enhancement operations. Beginning as early as Monday, July 14, the southbound lanes of Ocean Shore Boulevard between Standish Drive and Amsden Road will be closed for approximately three months. This is the last of three non-concurrent detour segments.
Detour maps can be found below under the 'Project Images' section. Please see the anticipated schedule from the Florida Department of Transportation (FDOT) below:
- Segment 1: The southbound lanes of Ocean Shore Boulevard will be closed between Neptune Avenue and East Granada Boulevard for approximately two months. Please note that the detour will be temporarily lifted for Daytona Bike Week and Spring Break from Friday, Feb. 28 through Sunday, Mar. 23. Construction activities will take place in the shoulder behind barrels. Roadway construction activities and the detour will resume on Monday, Mar. 24.
- Detour information: Motorists traveling south on Ocean Shore Boulevard wishing to reach East Granada Boulevard will turn right on Neptune Avenue, turn left on North Halifax Drive, and then continue south to East Granada Boulevard. This segment is complete.
- Segment 2: The southbound lanes of Ocean Shore Boulevard will be closed between Amsden Road and Neptune Avenue for approximately three months. This closure will be in place starting as soon as Wednesday, April 30.
- Detour information: Motorists traveling south on Ocean Shore Boulevard will be directed to turn right on to Amsden Road, turn left onto North Halifax Drive, and then continue south to East Granada Boulevard. From there, motorists can turn left to return to Ocean Shore Boulevard. Daytime flagging operations will be in place at the intersection of Amsden Road and Halifax Drive to facilitate traffic flow.
- Segment 3: The southbound lanes of Ocean Shore Boulevard will be closed between Standish Drive and Amsden Road for approximately three months. This closure will be in place starting as soon as Monday, July 14.
- Detour information: Motorists traveling south on Ocean Shore Boulevard wishing to reach East Granada Boulevard will turn right on Standish Drive, turn left on North Halifax Drive, and then continue south to East Granada Boulevard.
- Segment 1: The southbound lanes of Ocean Shore Boulevard will be closed between Neptune Avenue and East Granada Boulevard for approximately two months. Please note that the detour will be temporarily lifted for Daytona Bike Week and Spring Break from Friday, Feb. 28 through Sunday, Mar. 23. Construction activities will take place in the shoulder behind barrels. Roadway construction activities and the detour will resume on Monday, Mar. 24.