Project Details
Work Type: Resurfacing
Phase: Design
Length: 3.109 miles
City:
County:
Road:
Design Cost: $711,000
Letting: 12/01/2026
Estimated Costs
Construction Cost: $5.2 Million
About

The purpose of this project is to maintain the roadway surface by replacing all existing asphalt on State Road (S.R.) A1A from S.R. 520 to George King Boulevard in Cape Canaveral, Brevard County.  In addition to repaving the roadway, the project will upgrade pedestrian curb ramps as needed to comply with current Americans with Disabilities Act (ADA) requirements.

Contact Information
Design Project Manager
Gregory Prytyka
386-943-5394
Gregory.Prytyka@dot.state.fl.us