Project Details
Work Type: Resurfacing
Phase: Construction
Length: 6.515 miles
City:
County:
Road:
Construction Cost: $5.2 Million
Project Start: Early 2026
Est. Completion: Summer 2026
About

This project plans to mill and resurface State Road (S.R.) A1A from U.S. 1 (Ridgewood Avenue) in Daytona Beach Shores to Davis Street in Daytona Beach, including the bridge over the Halifax River.

Pedestrian safety enhancements including new and upgraded crosswalks are being designed under 450666-2.

Contact Information
Communications Team
Debbie Cople
(386) 740-3566
Debbie.Cople@dot.state.fl.us
Contractor
C. W. Roberts Contracting, Inc.
For Media Inquiries Only
FDOT-D5Comm@dot.state.fl.us
Lane Closures
  • Monday, Feb. 23, to Thursday, Feb. 26, from 7:30 a.m. to 5 p.m. the following morning: Motorists can expect outside single lane closures on southbound State Road (S.R.) A1A from Davis Street to Mobile Avenue to allow for the removal of concrete.

    FDOT encourages all roadway users to drive, walk and ride with caution and courtesy!