Project Details
Work Type: Resurfacing
Phase: Construction
Length: 10.612 miles
City:
County:
Road:
Construction Cost: $15.7 million
Project Start: Early 2021
Est. Completion: Summer 2022
About

The purpose of this project is to resurface U.S. 441 from State Road (S.R.) 35 (Baseline Road) to S.R. 200 (SW 10th Street). Additional improvements include modifications to extend left and right turn lanes at various locations, remove some of the existing on street parking, provide bicycle facilities within the right of way where possible, update and provide pedestrian features to meet current standards, and make other drainage and safety improvements, as needed. These improvements also include an almost half-mile portion of U.S. 27/U.S. 441 (SE Abshier Boulevard) east of County Road 484 (SE Hames Road).

The sidewalk gap and shared use path displayed in the attached project files are not included in this project.

Contact Information
Communications Team
Lynette Cruz
(352) 326-7744 / (352) 620-3020
Lynette.Cruz@dot.state.fl.us
Contractor
C. W. Roberts Contracting, Inc
Lane Closures
  • Sunday, May. 29, through Saturday, Jun. 4, from 7 p.m. to 7 a.m..: Motorists should expect northbound and southbound inside and outside lane closures on U.S. 441 from S.R. 35 to S.R. 200 for milling and paving as well as widening operations. Please slow down approaching the construction zone, merge safely into the open lane(s) and proceed cautiously through the work area.

    Sunday, May. 29, through Saturday, Jun. 4, from 9 a.m. to 4 p.m.: Motorists should expect northbound and southbound inside lane closures on U.S. 441 from S.R. 35 to S.R. 200 for drainage and widening operations. Please slow down approaching the construction zone, merge safely into the open lane(s) and proceed cautiously through the work area.

  • Sunday, May. 22, through Saturday, May. 28, from 7 p.m. to 7 a.m..: Motorists should expect northbound and southbound inside and outside lane closures on U.S. 441 from S.R. 35 to S.R. 200 for milling and paving as well as widening operations. Please slow down approaching the construction zone, merge safely into the open lane(s) and proceed cautiously through the work area.

    Sunday, May. 22, through Saturday, May. 28, from 9 a.m. to 4 p.m.: Motorists should expect northbound and southbound inside lane closures on U.S. 441 from S.R. 35 to S.R. 200 for drainage and widening operations. Please slow down approaching the construction zone, merge safely into the open lane(s) and proceed cautiously through the work area.

Project Files