EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

This project has been completed and is only available for historical reference.
Project Details
Work Type: Widening
Phase: Completed
Length: 13.850 miles
City:
County:
Road:
Construction Cost: $206.22 Million
Project Start: Early 2015
Est. Completion: Summer 2020
About
This project involves widening Interstate 95 (I-95) from four lanes to six lanes from north of State Road (S.R.) 44 to north of U.S. 92 (International Speedway Boulevard). The southern project limit will tie into the recently completed I-95 widening project to the south (from south of S.R. 406 to north of S.R. 44). The project scope also includes the reconstruction of the systems interchange with I-4, I-95 and U.S. 92.

Work to be done includes pavement widening, drainage systems improvements, bridge widening, bridge replacement, retaining walls, highway lighting, Intelligent Transportation System (ITS) modifications, median barriers, signing and pavement markings, signalization, milling, and resurfacing.

This project reconstructs the I-95 interchange leading to and from I-4 and U.S. 92, which will increase mobility and connectivity. It will also increase safety for merging, exiting and through-traffic. The project will eliminate a left-side merge ramp onto I-95 from U.S. 92, just a short distance to the south. Additional lanes will be constructed along I-95 allowing vehicles traveling through the area to continue in dedicated lanes, and vehicles entering and exiting I-95 to be separated into dedicated entrance and exit lanes.

Contact Information
Contractor
Archer Western Contractors
Communications Team
Debbie Cople
(386) 740-3566
Debbie.Cople@dot.state.fl.us
Project Files