Project Details
Work Type: Add Lanes
Phase: Construction
Length: 23 miles
City:
County:
Road:
Construction Cost: $257 Million
Project Start: Fall 2024
Est. Completion: Summer 2028
About

The Florida Department of Transportation is enhancing Interstate 75 (I-75) in Marion and Sumter counties, from south of State Road (S.R.) 44 to S.R. 200. A second project, which began in fall 2025, will focus on enhancements from S.R. 200 to S.R. 326 (FPID No. 452074-1) in Marion County.

Both projects will add auxiliary lanes to the interchanges, and in some locations, infrastructure improvements will be made. Improvements to several I-75 interchanges are proposed, including those at S.R. 326 and S.R. 40. The approved design will help relieve congestion on I-75 while providing resiliency for this heavily traveled roadway. Project documents are provided below.

Learn more about the Moving I-75 Forward projects online: (https://www.movingi75forward.com/). 

Additional project documents are available upon request as archived content for historical and research purposes.

Contact Information
Contractor
Anderson Columbia Co.
Communications Team
Tom McNiff
(352) 620-3005
Thomas.McNiff@dot.state.fl.us
For Media Inquiries Only
Lane Closures
  • Sunday, June 21, to Friday, June 26, from 8 p.m. to 6 a.m. nightly: Motorists are advised that there will be single and double lane closures on northbound I-75 between State Road 200 and County Road 484 for barrier wall installation and temporary paving work.

    FDOT is committed to building a transportation system that not only fits the current needs of Florida’s residents and visitors but also enhances mobility throughout the state to accommodate its consistent and rapid growth.

  • Monday, June 15, through June, 2027: Motorists are advised that the Southwest 66th Street bridge over I-75 is closed until mid-June 2027 for reconstruction. Motorists who wish to cross I-75 will instead be directed to use the SW 43rd Street Road bridge.

    Detour for motorists traveling east: Eastbound motorists may travel east on State Road 200 to SW 43rd Street Road, turn right, and proceed east across the SW 43rd Street Road bridge.

    Detour for motorists traveling west: Westbound motorists may travel north on SW 27th Avenue to Southwest 42nd Street and turn left, then travel west across the SW 43rd Street Road bridge and turn left on NW 40th Avenue or continue to State Road 200.