Project Details
Work Type: Bridge Repair
Phase: Completed
Length: 0.245 miles
City:
County:
Road:
Construction Cost: $2.1 Million
Project Start: Spring 2022
Est. Completion: Fall 2022
About

The purpose of this project is to remove and replace submarine cables underneath the North Causeway (State Road (S.R.) 44) moveable bridge over Indian River, also known as Coronado Beach Bridge, in New Smyrna Beach, Volusia County.

The submarine cables control the electricity that operates the machinery that allows the bridge to open and close for boat traffic to pass through. Replacing the existing cables will ensure continued operation of the bridge for all users.

Contact Information