448636-1 SR A1A Drainage Improvements
This project has been completed and is only available for historical reference.
Project Details
| Work Type: | Safety Project |
|---|---|
| Phase: | Completed |
| Length: | 0.03 miles |
| City: | |
| County: | |
| Road: | |
| Construction Cost: | $727,000 |
| Project Start: | Spring 2024 |
| Est. Completion: | Summer 2025 |
About
This project will include drainage improvements at three intersections on State Road (S.R.) A1A in Cocoa Beach. These intersections include:
- Northbound S.R. A1A at North 1st Street
- Southbound S.R. A1A at South 1st Street
- Southbound S.R. A1A at South 9th Street
This project will be constructed with the S.R. A1A Pedestrian Crossings project from Crescent Beach Drive to Minutemen Causeway (FPID No.: 445867-1).
Contact Information
| Contractor |
|---|
|
Carr Construction, LLC
|
| Communications Team |
|
Ashley Ingham
(321) 634-6111
Ashley.Ingham@dot.state.fl.us
|