Project Details
Phase: Construction
Length: 0.231 miles
County:
Road:
Construction Cost: $12.6 Million
Project Start: Spring 2026
Est. Completion: Fall 2027
About

The purpose of the project is to replace the northbound and southbound U.S. 1 (State Road (S.R.) 5) bridges over Pellicer Creek at the Flagler/St. Johns County line.

Contact Information
Contractor
C. W. Roberts Contracting, Inc.
Communications Team
Christine Batchelder
(386) 740-3564
Christine.Batchelder@dot.state.fl.us
For Media Inquiries Only
Lane Closures
  • Beginning June 11: Motorists are advised that a traffic shift on U.S. 1 (State Road (S.R.) 5) over Pellicer Creek at the Flagler-St. Johns County line will be implemented as early as Monday, June 8. The shift is necessary to accommodate the construction of a new northbound bridge and demolition of the old bridge.

    During this first phase, the northbound bridge will be closed, all northbound traffic will be shifted to the southbound bridge.

    Once the new northbound bridge is complete and the old bridge is demolished, all traffic will be moved onto the new northbound bridge. This will allow crews to close and replace the existing southbound bridge.

    Due to space limitations, the outside shoulders will be temporarily reduced to 1 foot during traffic shift operations. The median opening between Pellicer Creek Campground and Shantytown Village will be temporarily closed during construction. Navigational access for boats will be maintained.

    FDOT advises motorists to reduce their speed, follow posted signage, and exercise extra caution in the work zone. Construction schedules are subject to change due to inclement weather or other unforeseen circumstances.