Project Details
Work Type: Resurfacing
Phase: Construction
Length: 6.431 miles
City:
County:
Road:
Construction Cost: $7.9 Million
Project Start: Spring 2025
Est. Completion: Fall 2025
About

The Florida Department of Transportation (FDOT) is resurfacing State Road (S.R.) 50 from west of the S.R. 520 interchange to east of St. Anne Avenue in eastern Orange County, extending the life of the roadway.

Additional improvements include placing new asphalt to smooth turns onto S.R. 50 at various driveways and side streets, performing drainage and bridge repairs, and upgrading signing/pavement markings.

Contact Information
Communications Team
Ashley Ingham
(321) 634-6111
Ashley.Ingham@dot.state.fl.us
Lane Closures
  • Motorists are advised that the Florida Department of Transportation (FDOT) will implement nighttime ramp closures at State Road (S.R.) 50 and S.R. 520 beginning as early as Thursday, August 7. These closures are necessary for paving operations. 

    Please see the anticipated schedule and detour information below: 

    • The ramp from westbound S.R. 520 to eastbound S.R. 50 will be closed overnight from 8:30 p.m. Thursday, August 7, to 6:30 a.m. Friday August 8.
      • Detour: Motorists traveling westbound on S.R. 520 wishing to access eastbound S.R. 50 should exit onto westbound S.R. 50, make a U-turn at the first available median opening, and continue east on S.R. 50. 
  • 8 a.m. Monday, August 4, through 5 p.m. Friday, August 8

    Motorists can expect daily inside and outside single lane closures eastbound and westbound S.R. 50 from S.R. 520 to St. Anne Avenue.

    These closures are needed for miscellaneous construction activities.

    FDOT encourages all roadway users to drive, walk and ride with caution and courtesy!