Project Details
Work Type: Resurfacing
Phase: Completed
Length: 1.359 miles
City:
County:
Road:
Construction Cost: $3.4 million
Project Start: Spring 2023
Est. Completion: Spring 2024
About

The project is to resurface Princeton Street (State Road (S.R.) 438) from Chantelle Road to John Young Parkway (S.R. 423). Other improvements include minor drainage improvements, as well as sidewalk and curb ramp reconstruction in accordance with current Americans with Disabilities Act (ADA) standards.

Contact Information
Communications Team
Peyton Reese
(321) 319-8130
Peyton.Reese@dot.state.fl.us
Contractor
Atlantic Civil Constructors Corporation