Project Details
Work Type: Construction Work
Phase: Completed
City:
County:
Construction Cost: $341,000
Project Start: Spring 2020
Est. Completion: Fall 2020
About

The Florida Department of Transportation is installing an epoxy surface on two bridges spanning CSX rail lines along U.S. 441 in Ocala. One bridge is located roughly 1,500 feet north of State Road 40 (Silver Springs Boulevard), and the other is located about 1,500 feet north of U.S. 27 (Northwest 10th Street). Nighttime, single-lane closures will be routine during the approximately 180-day work timetable. Motorists are asked to exercise caution approaching the bridges.