Project Details
Work Type: Resurfacing
Phase: Construction
Length: 1.843 miles
City:
County:
Road:
Construction Cost: $9.3 Million
Project Start: Early 2021
Est. Completion: Spring 2022
About

This project will resurface Apopka-Vineland Road (State Road (S.R.) 535) from south of International Drive to south of Hotel Plaza Boulevard in Orange County. The portion of the project between north of Lake Bryan Beach Boulevard and Vineland Avenue will be included in Project 439237-1: SR 535 (Apopka-Vineland Road) from north of Lake Bryan Beach Boulevard to Vineland Avenue (https://www.cflroads.com/project/439237-1).

The project also includes new sidewalk construction, Americans with Disabilities Act (ADA) upgrades, drainage, signal, lighting and Intelligent Transportation Systems (ITS) improvements.

Contact Information
Communications Team
Shemir Wiles
(321) 319-8130
Shemir.Wiles@dot.state.fl.us
Contractor
Middlesex Corporation (The)
Lane Closures
  • Sunday, March 7, through Friday, March 12, from 11 p.m. to 6 a.m.: Northbound inside lane closure from World Center Drive to north of Meadow Creek Drive for median widening.

  • Sunday, March 7, through Friday, March 12, from 8 p.m. to 6 a.m.: Southbound inside lane closure from north of Meadow Creek Drive to north of World Center Drive for median widening.