EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Central Florida Roads

Florida Department of Transportation

Project Details
Work Type: Resurfacing
Phase: Construction
Length: 1.841 miles
City:
County:
Road:
Construction Cost: $3.44 Million
Project Start: Early 2020
Est. Completion: Early 2021
About
This project will resurface State Road (S.R.) 19 from Norton Avenue to Lake Saunders Drive. It will provide safety improvements for the S.R. 19 on ramp from eastbound U.S. 441, as well as an improved roadway transition to County Road 19A. Pedestrian and bike accommodations and ADA enhancements are also included.   
Contact Information
Contractor
D.A.B. Constructors, Inc.
(352) 352-3944
Communications Team
Thomas McNiff
(352) 620-3020
Thomas.McNiff@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.
Project Files