Project Details
Phase: Completed
Length: 0.084 miles
City:
County:
Road:
Construction Cost: $1.8 Million
Project Start: Spring 2023
Est. Completion: Early 2024
About

The intent of this project is to resolve flooding issues on U.S. 17-92/State Road (S.R.) 15/600 (North Woodland Boulevard) by constructing a bypass stormwater system.

The proposed improvements will incorporate additional drainage inlets, re-route existing flow patterns, and add new underground pipes along the median of North Woodland Boulevard and Mandarin Avenue.

This project will also clear median vegetation, relocate utilities, improve drainage and reconstruct pavement on North Woodland Boulevard and Mandarin Avenue.