Project Details
Work Type: Drainage Construction
Phase: Design
Length: 0.084 miles
City:
County:
Road:
Letting: 01/25/2023
Estimated Costs
ROW Cost: $286,000
Construction Cost: $1.2 Million
About

The intent of this project is to resolve flooding issues on U.S. 17-92/State Road (S.R.) 15/600 (North Woodland Boulevard) by constructing a bypass stormwater system.

The proposed improvements will incorporate additional drainage inlets, re-route existing flow patterns, and add new underground pipes along the median of North Woodland Boulevard and Mandarin Avenue.

This project will also clear median vegetation, relocate utilities, improve drainage and reconstruct pavement on North Woodland Boulevard and Mandarin Avenue.

Construction on this project is to begin spring 2023.