EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Work Type: Interchange Construction
Phase: Design
Length: 0.664 miles
County:
Road:
Letting: 02/23/2022
Estimated Costs
Construction Cost: $2.8 Million
About

The purpose of this project is to provide dual left turn lanes onto Interstate 95 (I-95) in both the eastbound and westbound directions from Wickham Road.  This project will also widen the northbound and southbound on ramps to accommodate two lanes of turning and merging traffic. New mast arms will also be installed.

Contact Information
Design Project Manager
Tyler Burgett
386-943-5439
Tyler.Burgett@dot.state.fl.us
Design Firm
KPM Franklin
(407) 410-8624