Project Details
Phase: Construction
Length: 0.384 miles
City:
County:
Road:
Construction Cost: $4.3 Million
Project Start: Early 2023
Est. Completion: Early 2024
About

The project begins south of State Road (S.R.) 40 (West Silver Springs Boulevard) on U.S. 441/U.S. 27/U.S. 301 (South Pine Avenue) and extends northward stretching between SW 3rd Street to NW 2nd Street.  The intent of the project is to implement traffic operation improvements and improve the life of the pavement through milling and resurfacing the existing travel lanes, and turn lane widening.

Minor drainage, pedestrian, sidewalk, intersection and signalization improvements are also a part of this project. The proposed improvements will add a dual left turn on northbound U.S. 441 to S.R. 40, and extend the left turn lane from southbound U.S. 441 to S.R. 40, and the northbound left turn from U.S. 441 to NW 2nd Street.

Contact Information
Communications Team
Matt Young
(352) 326-7744 / (352) 620-3020
MattA.Young@dot.state.fl.us
Contractor
C. W. Roberts Contracting, Inc.
For Media Inquiries Only
FDOT-D5Comm@dot.state.fl.us
Lane Closures
  • Monday, December 11, through Wednesday, January 31, 24 hours per day: Motorists should expect northbound outside lane closures on U.S. 441 from just south of West Fort King Street to Northwest 3rd Street for roadway widening. The intersection of U.S. 441 (South Pines Avenue) and S.R. 40 will be unaffected by the closure. Please slowly approach the construction zone, merge safely into the open lane(s), and proceed cautiously through the work area.

  • Thursday, December 7, and Sunday, December 10, through Thursday, December 14, form 9 p.m. to 6:30 p.m.: Motorists should expect nighttime northbound outside lane closures on U.S. 441 south of S.R. 40 for light pole and mast arm installation. Please slowly approach the construction zone, merge safely into the open lane(s), and proceed cautiously through the work area.

  • Monday, November 27, through Sunday, December 10, 24 hours per day: Motorists should expect northbound outside lane closures on U.S. 441 from Southwest 2nd Street north to S.R. 40 for roadway widening. Please slowly approach the construction zone, merge safely into the open lane(s), and proceed cautiously through the work area.