454207-1 S.R. 434 from U.S. 17-92 to S.R. 419
Project Details
| Work Type: | Resurfacing |
|---|---|
| Phase: | Design |
| Length: | 2.088 miles |
| City: | |
| County: | |
| Road: | |
| Design Cost: | $1.6 Million |
| Letting: | 12/01/2027 |
Estimated Costs
| Construction Cost: | $10.4 Million |
|---|
About
The purpose of this project is to enhance safety and operations along the corridor, as well as provide an updated asphalt surface to maintain the roadway. In addition to repaving State Road (S.R.) 434 from east of U.S. 17-92 to S.R. 419, the project will replace a portion of the two-way center left turn lane with a raised median and directional openings between Sheoah Boulevard and Charles Street.
Pedestrian safety improvements include reconstructing sidewalk curb ramps to meet current Americans with Disabilities Act (ADA) requirements, restore the pedestrian railing at the Sheoah Boulevard intersection, and refresh all crosswalk markings.
The existing traffic signals at Fountaintree Drive/Sunshadow Drive and at Winter Park Drive will be reconstructed and upgraded. Signal enhancements are also planned at the other existing signals along the corridor.
Get Involved
The FDOT will hold a project open house about this project on Thursday, August 20, from 5:30 p.m. to 7 p.m. at the Longwood Community Building at 200 W. Warren Ave., Longwood, FL 32750. Project materials will also be posted to this webpage, including all exhibits and the presentation, beginning on August 20.