454201-1 U.S. 301 from south of SR 44 to the Marion County Line
Project Details
| Phase: | Design |
|---|---|
| Length: | 8.4 miles |
| City: | |
| County: | |
| Road: | |
| Design Cost: | $841,500 |
| Letting: | 09/08/2027 |
Estimated Costs
| Construction Cost: | $19.6 Million |
|---|
About
This project plans to repave a segment of U.S. 301 (State Road (S.R.) 35) from south of S.R. 44 to the Marion County line in Sumter County. The project is needed to maintain the roadway. Improvements will provide a smoother driving surface and enhance safety by refreshing the pavement markings and upgrading signs. Pedestrian safety will be enhanced by upgrading sidewalk curb ramps to comply with current Americans with Disabilities Act (ADA) requirements.
Contact Information
| Design Project Manager |
|---|
|
Aleacia Spann
(386) 943-5234
Aleacia.Spann@dot.state.fl.us
|