Project Details
Phase: Design
Length: 0.556 miles
City:
County:
Road:
Letting: 09/06/2028
Estimated Costs
Construction Cost: $1.5 Million
About

This project proposes to resurface approximately one-half mile of U.S. 441 (Orange Blossom Trail) from Cabell Lane to Citrus Avenue in Apopka, Orange County. The purpose of this project is to rehabilitate the asphalt pavement to maintain a safe and reliable driving surface. The project will include upgrades to pedestrian curb ramps as needed to comply with current Americans with Disabilities Act (ADA) standards and to restore existing signalization detection impacted by repaving operations.

Contact Information
Design Project Manager
Matthew Gallup
(386) 943-5189
Matthew.Gallup@dot.state.fl.us