EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Work Type: Erosion Protection
Phase: Construction
City:
County:
Road:
Construction Cost: $80 Million
About

The Florida Department of Transportation (FDOT) will construct buried seawalls in two locations in northern Volusia County to provide long-term protection for State Road (S.R.) A1A. The first location is from south of Sunrise Avenue to Marlin Drive. The second location begins one-half mile north of High Bridge Road to the Flagler County line. From the county line, the wall continues north and will end at South Central Avenue in Flagler County.  That wall portion is covered under project 452444-1.

Work is expected to begin in February 2024 in Flagler County.  Work on the Volusia County portions is expected to start by summer 2024.

The project was recommended in the S.R. A1A Resiliency Plan, which was a joint effort by representatives from the FDOT, Flagler County, the City of Flagler Beach, and Volusia County to explore options to repair and strengthen S.R. A1A in Flagler and Volusia counties. 

 

Contact Information
Contractor
Superior Construction Company Southeast, LLC
Communications Team
Amber Mullins
amber.mullins@dot.state.fl.us
For Media Inquiries Only
FDOT-D5Comm@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.
Goes With
Project Files