450577-1 SR 527 / Orange Ave southbound from Magnolia Ave to SR 50
Project Details
Estimated Costs
Construction Cost: | $1.2 Million |
---|
About
This is a maintenance resurfacing project on southbound Orange Avenue (State Road (S.R.) 527) from Magnolia Avenue to S.R. 50. The project will also upgrade pedestrian curb ramps as needed to comply with current Americans with Disabilities Act (ADA) standards.
Contact Information
Design Project Manager |
---|
Samuel Jumber
(386) 943-5244
Samuel.Jumber@dot.state.fl.us
|
Design Firm |
Johnson, Mirmiran & Thompson
|