Project Details
Work Type: Resurfacing
Phase: Construction
Length: 24.1 miles
City:
County:
Road:
Construction Cost: $63.3 Million
Project Start: Early 2025
Est. Completion: Spring 2027
About

The Florida Department of Transportation (FDOT) is resurfacing 24 miles of northbound and southbound Interstate 95 (I-95) from south of Malabar Road (State Road (S.R.) 514) to north of Fiske Boulevard (S.R. 519). The ramps at the following interchanges will also be repaved: Malabar Road, Palm Bay Road (County Road (C.R.) 516), U.S. 192, S.R. 518 (Eau Gallie Boulevard), S.R. 404 (Pineda Causeway), Wickham Road, and Fiske Boulevard.

Other improvements include building barriers to protect the overpass piers at Minton Road, S.R. 404, and Viera Boulevard, applying new deck coatings on the bridges over S.R. 518 and Lake Washington Road, upgrading pavement markings, and improving the Intelligent Transportation System (ITS).

Contact Information
Communications Team
Ashley Ingham
(321) 634-6111
Ashley.Ingham@dot.state.fl.us
Contractor
C. W. Roberts Contracting, Inc.
For Media Inquiries Only
Lane Closures
  • Sunday, March 22 through Thursday, March 26, from 7 p.m. to 7 a.m.: Motorists can expect inside single-lane closures northbound S.R. I-95 from Pineda Causeway (Exit 188) to Fiske Boulevard (Exit 195).

    These closures are needed for paving activities.

    FDOT encourages all roadway users to drive, walk and ride with caution and courtesy! 