448915-1 I-4 Interchange at SR 528
Project Details
About
The purpose of this project is to add capacity to the I-4 westbound on-ramp to eastbound State Road 528 (the Beachline Expressway) by widening the ramp from one to two lanes.
The project began in January 2024 and is anticipated to reach completion in 2026.
For more information, please visit I4Beyond.com/SR528.
Contact Information
Communications Team |
---|
Dom Scalise
(973) 879-2253
info@i4Beyond.com
|
Communications Team |
Annabelle Bruzos Vega
(321) 319-8130
Annabelle.BruzosVega@dot.state.fl.us
|
Lane Closures
-
- 06/08/25 to 06/13/25
- Westbound I-4 exit ramp to eastbound S.R. 528
- 10 p.m. – 6 a.m.
- 06/11/25 to 06/13/25
- Westbound I-4 from Kirkman Road to S.R. 528
- 10 p.m. – 6 a.m.
- *06/15/25 to 06/16/25
- Westbound I-4 from Kirkman Road to S.R. 528
- 10 p.m. – 6 a.m.
- *06/15/25 to 06/18/25
- Eastbound I-4 under S.R. 528
- Westbound I-4 exit ramp to eastbound S.R. 52810 p.m. – 6 a.m.
- 6/15/25 is a “swing” date. Depending on their progress next week, they will either have the full westbound I-4 detour or the full eastbound I-4 detour, but not both.
- 06/08/25 to 06/13/25