Project Details
Work Type: Parking Facility
Phase: Construction
Length: 0.447 miles
City:
County:
Road:
Construction Cost: $19.82 Million
Project Start: Fall 2026
Est. Completion: Early 2028
About

This project will build a new designated truck parking facility near Interstate 4 (I-4) in Seminole County to serve Central Florida and support the state's freight industry. This project is the first being undertaken by District 5 to address the high demand for safe truck parking along the I-4 corridor. Due to economic growth and the resulting increase in the demand for the delivery of goods, the need for safe parking facilities along our Interstates has become a critical issue for all drivers and our I-4 communities.

The facility will be located on a parcel in the southeast quadrant of the I-4 and U.S. 17-92 interchange. Trucks will have the option of utilizing Exit 101 and S.R. 46 or Exit 104 and U.S.17-92 to access the facility. The Seminole County site will provide 132 spaces and include restrooms, on-site security, lighting, sidewalks/pet walk areas, picnic areas, and landscaping.

The site is one of five locations identified through the Truck and Freight Alternative Site Analysis Project Development & Environment (PD&E) Study (FPID No.: 447724-1). The other four sites are being designed under the following project numbers: Volusia County eastbound 446445-2; Volusia County westbound 446445-4; Osceola County 446445-5 and Orange County 446445-3.

Contact Information
Communications Team
Ryan Yglesias
(407) 278-2713
Ryan.Yglesias@dot.state.fl.us
For Media Inquiries Only
Lane Closures
  • There are no lane closures at this time.
Project Files