EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Phase: Design
Length: 0.075 miles
County:
Road:
Design Cost: $806,000
Letting: 07/30/2025
Estimated Costs
Construction Cost: $1.9 Million
About

The purpose of this project is to reconstruct and upgrade the existing traffic signal at the intersection of Orange Blossom Trail (U.S. 441/ State Road 500) and Clarcona-Ocoee Road to include new poles, new signal heads with enhanced visibility for drivers, and new pedestrian signals. Additional intersection improvements include the extension of the eastbound right turn lane.

A public meeting for this project was held on February 1, 2022. Please see the meeting information in the files below.

Contact Information
Design Project Manager
Samuel Jumber
(386) 943-5244
Samuel.Jumber@dot.state.fl.us
Design Firm
Protean Design Group, Inc.
Project Files