Project Details
Work Type: Resurfacing
Phase: Design
Length: 1.41 miles
City:
County:
Road:
Design Cost: $745,000
Letting: 01/03/2024
Estimated Costs
Construction Cost: $3.8 Million
About

The intent of this project is to resurface South Street (State Road 405) from south of Bobbi Lane to north of Swan Lake Drive to extend the life of the roadway. Pedestrian safety improvements include replacing the existing 6-foot-wide sidewalk with an 8-feet-wide path along the west side of South Street, which will extend the existing 8-foot-wide path from Fox Lake Road to North of Swan Lake Drive. A new 6-foot-wide sidewalk will also be constructed along the east side of South Street from Fox Lake Road to North of Joe Murell Drive.

Other improvements include upgrades to intersection lighting, improved crosswalks with median refuge areas, upgraded transit stops, and minor widening at turn lanes to provide bicycle through lanes. Additionally, the project plans to help encourage safer driving speeds by introducing small curves in the road, reducing lane widths, adding raised medians, and replacing the two-way-left-turn lanes with dedicated left turn lanes and spot medians throughout the corridor. The raised medians will not impact access to any side streets or driveways.

A public meeting about the project was held February 7, 2023. Please see the public meeting information in the files below.

Contact Information
Design Project Manager
Kevin Powell
(386) 943-5425
Kevin.Powell@dot.state.fl.us
Design Firm
WSP USA Inc.
Project Files