Project Details
Work Type: Resurfacing
Phase: Construction
Length: 0.316 miles
City:
County:
Road:
Construction Cost: $1.6 Million
Project Start: Late 2022
Est. Completion: Spring 2023
About

The purpose of this project is to extend the life of the existing roadway by repaving Montreal Avenue from U.S. 1 to Pineapple Avenue and improve pedestrian and bicycle safety along the corridor.  Proposed design elements include adding landscaped curb extensions, removing six on-street parking spaces from the outside right lane, adding 11 on-street-parking spaces to the inside left lane, adding a 7-foot-wide buffered bike lane, and modifying existing sidewalks.

Contact Information
Communications Team
Tina Thomas
(321) 634-6111
Tina.Thomas@dot.state.fl.us
Lane Closures
  • Monday, March 27, through Thursday, March 30, between 9 p.m. and 7 a.m., 

    Motorists can expect lane closures on S.R. 518/ Montreal Avenue from U.S. 1 to Pineapple Avenue

    These closures are needed for milling and paving operations. 

    Please proceed with caution in construction zones.

  • Semi-permanent closure: Monday through Friday during construction

    Motorists can expect shoulder closures along S.R. 518/ Montreal Avenue from U.S. 1 to Pineapple Avenue

    These closures are needed for milling and paving operations. 

    Please proceed with caution in construction zones.