Project Details
Work Type: Widening
Phase: Design
Length: .867 miles
County:
Road:
Letting: 12/02/2020
Estimated Costs
Construction Cost: $2.6 Million
About
The purpose of this project is to add a center turn lane on State Road (S.R.) 60 from east of S.R. 15/U.S. 441 to west of S.R. 91/Florida's Turnpike. The addition of the center turn lane is to reduce congestion along the S.R. 60 corridor and improve the traffic operations at the Turnpike's on and off ramps and U.S. 441 intersection.
Contact Information
Design Firm
Dewberry Engineers, Inc
Design Project Manager
Samuel Jumber
(386) 943-5244
samuel.jumber@dot.state.fl.us
Goes With