Project Details
Work Type: Resurfacing
Phase: Construction
Length: 6.387 miles
City:
County:
Road:
Construction Cost: $6.9 Million
Project Start: Summer 2021
Est. Completion: Early 2022
About

The purpose of this project is to mill and resurface North Courtenay Parkway (State Road (S.R.) 3) from S.R. 528 to the Kennedy Space Center property line.

Contact Information
Communications Team
Tina Thomas
(321) 634-6111
Tina.Thomas@dot.state.fl.us
Contractor
VA Paving
Lane Closures
  • Monday, November 29 - Friday, December 3, from 9 a.m. to 3 p.m.,

    Motorists can expect lane closures of northbound and southbound travel lanes between the Smith/Grant Road and Hall Road.

    These closures are necessary for pouring concrete structures and daytime paving.

    Please proceed with caution in construction zones.