438982-1 US 1 from 6th Street to Flomich Street
Project Details
Work Type: | Intersection Construction |
---|---|
Phase: | Design |
Length: | 1.833 miles |
City: | |
County: | |
Road: | |
Design Cost: | $691,000 |
Letting: | 01/26/2022 |
Estimated Costs
ROW Cost: | $1.4 Million |
---|---|
Construction Cost: | $2 Million |
About
This project will update signals and replace current strain poles with mast arms. It includes the design of four intersections along U.S. 1 (locally known as Ridgewood Avenue) at 6th Street, 8th Street, Walker Street and Flomich Street.
Contact Information
Design Firm |
---|
Traffic Engineering Data Solutions, Inc
|
Design Project Manager |
Todd Long
(386) 943-5558
todd.long@dot.state.fl.us
|