This project has been completed. The information on this webpage is archived for reference and research purposes.
Project Details
Work Type: Drainage Construction
Phase: Completed
Length: 0.21 miles
County:
Road:
Construction Cost: $1.8 Million
Project Start: Early 2020
Est. Completion: Early 2021
About

The purpose of this project is to replace and re-align the existing drainage culvert on U.S. 1 in Rockledge. The project limits run south on U.S. 1 from Topsail Drive to Ernest Sands Road. Once complete, the new drainage structure will reduce flooding in the area during and after heavy rainfalls. Additional improvements include milling and resurfacing, new guardrail and pavement markings.

Contact Information
Communications Team
Ashley Ingham
(321) 634-6111
Ashley.Ingham@dot.state.fl.us