Project Details
Work Type: Resurfacing
Phase: Construction
Length: 1.797 miles
County:
Road:
Construction Cost: $11.25 Million
Project Start: Summer 2021
Est. Completion: Spring 2024
About

The Florida Department of Transportation (FDOT) is resurfacing and implementing safety improvements on State Road (S.R.) 551 (Goldenrod Road) from S.R. 408 to S.R. 50. Safety improvements include widening the lanes to make room for bike lanes, constructing raised medians, upgrading traffic signals, and lighting and improving drainage.

Contact Information
Contractor
Southland Construction, Inc.
Communications Team
Stephen Foy
(407) 278-2713
stephen.foy@dot.state.fl.us
Lane Closures
  • Beginning Monday, Mar. 20, through Friday, Apr. 20, between 9 a.m. and 3 p.m., the outside lane on southbound Goldenrod State Road (S.R.) 551 from Golden Glenn Drive to Chapel Trace Drive will be closed to allow the contractor to widen the roadway and complete signalization work. 

    With the potential for adverse weather issues, including morning fog, motorists are advised to exercise caution and stay alert as they travel through construction zones, even when no workers may be present.

  • The southbound Goldenrod State Road (S.R.) 551 outside lane is temporarily closed. Motorists are being shifted to utilize the bi-directional middle lane at the second southbound thru traffic lane from (S.R.) 50 to Yucatan Drive.

    With the potential for adverse weather issues, including morning fog, motorists are advised to exercise caution and stay alert as they travel through construction zones, even when no workers may be present.

Project Files