Project Details
Work Type: Sidewalk
Phase: Construction
Length: 1.423 miles
City:
Road:
Construction Cost: $812,000
About

The intent of this project is to remove the existing 4.5-foot concrete and 4-foot asphalt path on the north side of the road and replace it with an 8-foot concrete sidewalk. The new 8-foot sidewalk will meet FDOT and Americans with Disabilities Act (ADA) requirements. 

This project is located within the City of Ocala between NW 27th Avenue and the downtown area.

Contact Information
Communications Team
Natecia Gayle
(352) 326-7744 / (352) 620-3020
Natecia.Gayle@dot.state.fl.us
Lane Closures
  • Monday, March 27, through Thursday, March 30, from 7 p.m. to 6 a.m.: Motorists should expect eastbound and westbound nighttime lane closures from NW 27th Avenue to SW 7th Avenue for signal operations. Please slow down when approaching the construction zone, merge safely into the open lane(s) and proceed cautiously through the work area.

Project Files