437116-1 US 1 Drainage Outfall from north of Cross Road to Indian River Drive
Project Details
Estimated Costs
ROW Cost: | $139,000 |
---|---|
Construction Cost: | $1.8 Million |
About
This project will rehabilitate an existing FDOT drainage ditch that carries water from U.S. 1 to the Indian River Lagoon. To assist the State Road (S.R.) 528 widening project (407402-2), this project also includes the re-construction of historic drainage pipes from the infield ponds at the intersection of S.R. 528 and U.S. 1 to drain the ponds westward, under U.S. 1 and the Florida East Coast Railway. A pond is also being constructed for compensatory treatment for S.R. 528, near the U.S. 1 ditch.
Contact Information
Design Project Manager |
---|
Marcus Lisicki
(386) 943-5542
Marcus.Lisicki@dot.state.fl.us
|
Design Firm |
Consor Engineers, LLC
|