Work Type: Intersection Construction
Phase: Construction
Length: 2.975 miles
City:
County:
Road:
Construction Cost: $3.99 Million
Project Start: Spring 2020
Est. Completion: Early 2021
About

The purpose of this project is to make improvements along State Road (S.R.) 405 (Columbia Boulevard) at the intersections of S.R. 50, Barna Avenue and Grissom Parkway. The proposed improvements are part of the Spaceport Strategic Intermodal System (SIS).