433654-1 SR 500/US 192 at Wickham Road
This project has been completed. The information on this webpage is archived for reference and research purposes.
Project Details
| Work Type: | Add Turn Lane |
|---|---|
| Phase: | Completed |
| Length: | .020 miles |
| City: | |
| County: | |
| Road: | |
| Construction Cost: | $1.4 Million |
| Project Start: | Summer 2018 |
| Est. Completion: | Summer 2019 |
About
The Florida Department of Transportation (FDOT) will build a new eastbound right turn lane and add a second northbound left turn lane at the intersection of S.R. 500/U.S. 192 (W. New Haven Avenue) and Wickham/Minton Road.
Contact Information
Contractor
Masci General Contractor, Inc.
Communications Team
Ashley Ingham
(321) 634-6111
Ashley.Ingham@dot.state.fl.us