242626-2 SR 93 (I-75) from Hernando County Line to CR 470
This project has been completed. The information on this webpage is archived for reference and research purposes.
Project Details
About
This project widened Interstate 75 (I-75) from four lanes to six lanes, completely reconstructing the interchange at Exit 314 [State Road (S.R.) 48/County Road (C.R.) 48], updating the ramps including milling and resurfacing at Exit 309 (C.R. 476B/C.R. 673), added/adjusted drainage, upgraded the Intelligent Transportation Systems (ITS), and added/changed guardrail, signalization, signing and pavement markings and other miscellaneous structures.
Note: In April 2018, surveying will be conducted on this project as a post-construction activity.
Contact Information
Contractor
Middlesex Corporation (The)
Communications Team
Annabelle Bruzos Vega
(321) 319-8130
Annabelle.BruzosVega@dot.state.fl.us