Project Details
Work Type: Intersection Construction
Phase: Design
Length: 0.575 miles
City:
County:
Road:
Design Cost: $1.4 Million
Letting: 06/06/2023
Estimated Costs
Construction Cost: $8.2 MIllion
About

The purpose of the County Road (C.R.) 46A (H.E. Thomas Parkway) and Rinehart Road intersection improvement project is to increase traffic efficiency while reducing congestion onto the Interstate 4 (I-4) and C.R. 46A interchange. The proposed enhancements will increase capacity at the intersection by modifying select existing turn lanes and adding new turn lanes. Construction is anticipated to start in fall of 2023.

For the most up-to-date project information, please visit:  C.R. 46A and Rinehart Road intersection project. 

Contact Information
Design Project Manager
Abhijeet Desai
(386) 943-5591
Abhijeet.Desai@dot.state.fl.us
Design Firm
WSP USA Inc.