240836-1 SR 40 from SR 15/US 17 to west of SR 11
Project Details
Estimated Costs
ROW Cost: | $5 Million |
---|---|
Construction Cost: | $35 Million |
About
The purpose of this project is to mill and resurface existing roadway to serve as westbound travel lanes, and construct new roadway for eastbound travel lanes to the south of the existing road.
The plan also includes four box culverts that will be used to accommodate wildlife crossings. Two of those crossings are 4 feet high and 10 feet wide; one is 8 feet high by 19 feet wide; and the fourth is 5 feet high by 6 feet wide. Also, the project will construct a 12-foot wide, paved, multi-use trail on the south side of the road.
Contact Information
Design Project Manager |
---|
Taleb Shams
(386) 943-5231
taleb.shams@dot.state.fl.us
|
Design Firm |
Kisinger Campo Assoc.
|