Project Details
Work Type: Resurfacing
Phase: Construction
Length: 13.993 miles
City:
County:
Road:
Construction Cost: $28.4 Million
Project Start: Early 2023
Est. Completion: Fall 2024
About

The purpose of this project is to resurface Interstate 75 ( I-75) from the Sumter County line to State Road (S.R.) 200. In addition, the existing median crossovers will be reconstructed, the guardrail will be updated and added where necessary, and minor drainage work will take place.

Contact Information
Communications Team
Matt Young
(352) 326-7744 / (352) 620-3020
MattA.Young@dot.state.fl.us
Contractor
Anderson Columbia Co.
For Media Inquiries Only
FDOT-D5Comm@dot.state.fl.us
Lane Closures
  • Double Lane Closure on Southbound I-75 just South of S.R. 200 for Emergency Repair

    The middle and outside southbound lanes on Interstate 75 (I-75) near mile marker 349, just south of State Road (S.R.) 200, are temporarily closed for an emergency asphalt repair. Expect delays and consider an alternate route.

    The Department is implementing our rapid repair plan. Once the repair is made, the Department will continue to monitor the roadway. It is unknown when the lanes will be reopened.

     

    I-75 Southbound On-Ramp at S.R. 200 to be Temporarily Closed Starting at 8 p.m. on April 24

    The Interstate 75 (I-75) southbound on-ramp at State Road (S.R.) 200 will be closed overnight starting at 8 p.m. on Wednesday, April 24, to aid in the asphalt repair that began the afternoon of April 24, on I-75 near mile marker 349. Once the repair is complete, the ramp is expected to reopen by 7:30 a.m. on Thursday, April 25.

    Detour Information:

    • Motorists traveling southwest on S.R. 200 will turn left on SW 60th Avenue, left on SW 95th Street, right on SW 49th Avenue Road, and left on County Road (C.R.) 484 to I-75.
    • Motorists traveling northeast on S.R. 200 will turn right on SW 43rd Street Road/42nd Street/32nd Street, right on C.R. 475, and right on C.R. 484 to I-75.

     

    The anticipated work schedule is subject to change due to weather and unforeseen circumstances.

  • Sunday, April 21, through Friday, April 26, from 8 p.m. to 6 a.m.: Motorists should expect overnight northbound and southbound lane closures on Interstate 75 (I-75) from C.R. 484 to S.R. 200 for milling and paving and median grade improvements, and guardrail installation. Please reduce your speed, alertly merge into an open lane and cautiously bypass the construction zone.