Construction Work on SR 50 in Orange County near City of Ocoee
  • Saturday, January 21st, 2017 to Tuesday, March 7th, 2017

    Asplundh is requesting a night time single lane closure at SR 50 under SR 429 beginning February 21 through March 17, 10 p.m. to 7 a.m.

     

    A single lane closure with traffic tapered into the left travel lane under SR 429. Contractor to furnish and install LED underdeck wall mount luminaires, and demo existing pendant luminaires. Most of the work will be off the shoulder and will not affect traffic.

     

    The Contractor will however, need to shift traffic into the left travel lane for "short durations" between the hours of 10 p.m. to 7 a.m., Monday night through Friday morning. Florida Highway Patrol (FHP) Officers will be onsite for the duration of the lane closures.

     

    Project #

    434946-3-52-01

    District

    08 | Turnpike Enterprise

    Contract Description

    BRIDGE UNDERDECK LIGHTING UPGR

     

    David Pruitt

    Sanford, FL 32771

    (407) 328-3131 Office

    dpruitt1@asplundh.com

     

Resurfacing on SR 50 in Orange County near City of Orlando [432407-1] View Project
  • Sunday, February 19th, 2017 to Saturday, February 25th, 2017

    10 p.m. to 6 a.m.

    Eastbound inside (right) lane closure on Colonial Drive (State Road 50) at Orange Avenue.

    East and west bound outside (right) lane closure on Colonial Drive (State Road 50) at Elwood Avenue.

     

    Crews will be working on changing out signal controller cabinet, saw cutting TMS and axle sensors.

Bridge Construction on SR 50 in Orange County near City of Orlando [433607-1] View Project
  • Sunday, February 19th, 2017 to Saturday, February 25th, 2017

    ·       Daytime Closures, Monday - Saturday, 9 a.m. - 5 p.m.

    o   Monday, February 20, 2017 – Saturday, February 25, 2017

    ·       Nighttime Closures, Sunday – Saturday, 6:30 p.m. - 6 a.m.

    o   Sunday night, February 19, 2017 – Saturday morning, February 25, 2017

     

    The contractor will be closing the eastbound and westbound inside and outside lanes on SR 50 from just east of Avalon Park Boulevard to Masood Lane. The lanes in each direction will be closed one at a time.

     

    Contractor’s work will include installing delineators, unloading construction equipment and road work.