This project will reconstruct U.S. 17/92 from Shepard Road to Lake Mary Boulevard from a rural four-lane roadway to an urban six-lane roadway. This contract includes construction of a new bridge to replace the existing box culvert at Soldiers Creek.

It also includes milling and resurfacing, drainage improvements, signing and pavement makings, lighting, signals, and Intelligent Transportation Systems (ITS). Additionally, water mains and force mains for the City of Sanford and Seminole County will be installed.

This project has been combined with:

  • 240196-1-56-01 – City of Sanford (Water Main & Force Main)
  • 240196-1-56-02 – City of Sanford (6” Force Main around Exfiltration System)
  • 240196-1-56-03 – Seminole County (Water Main & Force Main)
Lane Closures
  • Monday, March 19th, 2018 to Sunday, December 1st, 2019

    Detour of General Hutchison Parkway in Longwood, Seminole County

    Motorists that regularly travel General Hutchison Parkway are advised of the extended closure of the road from U.S. 17/92 to east of Big Tree Park.

    The closure of General Hutchison Parkway is necessary for construction crews to safely raise the road, construct the southbound phase of the bridge over Soldiers Creek and widen southbound U.S. 17/92 from Bill Ray Nissan to Shepard Road. 

    During the closure, General Hutchison Parkway may be accessed by one of two detours:

        ·            U.S. 17/92 to westbound Ronald Reagan Boulevard or

        ·            U.S. 17/92 to westbound State Road (S.R.) 434 to northbound Ronald  

                  Reagan Boulevard.   

    Unforeseen utility work, revisions to plans for retaining walls and some design modifications in this area of work caused delays to opening General Hutchison Parkway.

    General Hutchison Parkway is anticipated to reopen by early December 2019 pending weather and other unforeseen circumstances.  

    To ensure your safety and the safety of others, please use extra caution when driving through construction work zones.

     

  • Sunday, November 10th, 2019 to Saturday, November 16th, 2019

    Sunday – Friday, 7:30 p.m. – 6:30 a.m.: Alternating nighttime single lane closures throughout the northbound and southbound directions of the project. Construction crews will be paving, installing storm drainage, and working with traffic signals.

  • Tuesday, November 12th, 2019 to Friday, November 15th, 2019

    Tuesday – Thursday, 9 a.m. – 3 p.m.: Alternating single lane closure on US 17/92 southbound from ¼ mile south of Silkwood Court to Raven Avenue. Construction crews will be widening roadways and installing storm drainage.

    Tuesday – Thursday, 9 a.m. – 3 p.m.: Right lane closure at westbound County Home Road from 500 feet east of US 17/92 to US 17/92. Crews will be constructing new sidewalk.

    Tuesday – Thursday, 9 a.m. – 3 p.m.: Right lane closure at eastbound County Home Road from 500 feet west of US 17/92 to US 17/92. Crews will be constructing new sidewalk.

  • Wednesday, November 13th, 2019 to Thursday, November 14th, 2019

    Wednesday, 9 a.m. - 3 p.m.: Right turn lane closure at westbound State Road 419 onto northbound US 17/92. The lane will be closed in 15-minute increments only allowing traffic queues to clear out before closing the lane again. The lane closure will allow concrete placement for a pedestrian access ramp.