EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Skip to Content
About

This project will reconstruct U.S. 17/92 from Shepard Road to Lake Mary Boulevard from a rural four-lane roadway to an urban six-lane roadway. This contract includes construction of a new bridge to replace the existing box culvert at Soldiers Creek.

It also includes milling and resurfacing, drainage improvements, signing and pavement makings, lighting, signals, and Intelligent Transportation Systems (ITS). Additionally, water mains and force mains for the City of Sanford and Seminole County will be installed.

This project has been combined with:

  • 240196-1-56-01 – City of Sanford (Water Main & Force Main)
  • 240196-1-56-02 – City of Sanford (6” Force Main around Exfiltration System)
  • 240196-1-56-03 – Seminole County (Water Main & Force Main)
Lane Closures
  • Monday, March 19th, 2018 to Sunday, December 1st, 2019

    Detour of General Hutchison Parkway in Longwood, Seminole County

    Motorists that regularly travel General Hutchison Parkway are advised of the extended closure of the road from U.S. 17/92 to east of Big Tree Park.

    The closure of General Hutchison Parkway is necessary for construction crews to safely raise the road, construct the southbound phase of the bridge over Soldiers Creek and widen southbound U.S. 17/92 from Bill Ray Nissan to Shepard Road. 

    During the closure, General Hutchison Parkway may be accessed by one of two detours:

        ·            U.S. 17/92 to westbound Ronald Reagan Boulevard or

        ·            U.S. 17/92 to westbound State Road (S.R.) 434 to northbound Ronald  

                  Reagan Boulevard.   

    Unforeseen utility work, revisions to plans for retaining walls and some design modifications in this area of work caused delays to opening General Hutchison Parkway.

    General Hutchison Parkway is anticipated to reopen by early December 2019 pending weather and other unforeseen circumstances.  

    To ensure your safety and the safety of others, please use extra caution when driving through construction work zones.

     

  • Sunday, July 21st, 2019 to Friday, July 26th, 2019

    Contractor will have alternating single lane closure on alternating inside and outside lanes on northbound and southbound US 17/92 between Shepard Road and Lake Mary Blvd.

     

    They will be working on barrier wall removal, traffic signal installation and asphalt paving. Work will begin Sunday, July 21 through Friday, July 26 from 7:30 p.m. to 6:30 a.m.

Project Files