Project Details
Work Type: Resurfacing
Phase: Design
Length: 2.02 miles
City:
County:
Road:
Design Cost: $781,000
Letting: 02/01/2028
Estimated Costs
Construction Cost: $4.5 Million
About

This is a maintenance resurfacing project on State Road 406 (Garden Street) from west of the Interstate 95 (I-95) interchange to Forrell Avenue, excluding the I-95 ramps. A separate project will be making improvements the I-95 and S.R. 406 interchange as part of a resurfacing project on I-95 from S.R. 50 to S.R. 46. That project is FPID No. 450771-1.

Please note the construction start has changed.  Work is now expected to begin in spring 2028.

Get Involved

The FDOT held a public meeting about this project on Thursday, August 22, 2024. The meeting materials are in the files below.

Contact Information
Design Project Manager
Gregory Prytyka
(386) 943-5394
Gregory.Prytyka@dot.state.fl.us
Design Firm
Connect Engineering, LLC
Project Files