Project Details
Work Type: Safety Project
Phase: Construction
Length: 3.104 miles
County:
Road:
Construction Cost: $7 Million
Project Start: Early 2024
Est. Completion: Spring 2025
About

The purpose of the project is to provide median modifications on U.S. 17 (State Road 15) from Spring Garden Avenue (State Road 15A) to south of Spring Street.

Contact Information
Communications Team
Britney Jones
(386) 740-3566
Britney.Jones@dot.state.fl.us
Contractor
Southland Construction, Inc.
Lane Closures
  • Starting Monday, March 25, the travel lanes on US 17 from SR 15A to south of Spring Street will be reduced to one outside lane in each direction from north of Retta Street to north of Berlins Street for traffic separator construction. The median crossover at Reynolds Road/Wheeler Street will remain open during this work.