EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Central Florida Roads

Florida Department of Transportation

Project Details
Work Type: Resurfacing
Phase: Design
Length: 3.882 miles
City:
County:
Road:
Letting: 04/05/2022
Estimated Costs
Construction Cost: $7.4 Million
About

This project will resurface U.S. 17-92 (Orange Blossom Trail/John Young Parkway) from east of Ham Road to south of Portage Street to extend the life of the roadway. The project will construct concrete islands at the intersection of U.S. 17-92 and Pleasant Hill Road to facilitate new pedestrian crosswalks and widen some right turn lanes to accommodate bicycle through lanes. The project also includes drainage improvements, shoulder widening, new sidewalk construction to fill some existing gaps where possible, curb ramp reconstruction, and traffic signal upgrades.

Contact Information
Design Project Manager
Naziru Isaac
(386) 943-5547
Naziru.Isaac@dot.state.fl.us