Project Details
Work Type: Resurfacing
Phase: Completed
Length: 6.663 miles
City:
County:
Road:
Construction Cost: $6.5 Million
Project Start: Early 2022
Est. Completion: Early 2023
About

The purpose of this project is to rehabilitate the existing pavement on U.S. 1 (State Road 5) from the Brevard County line to South Street in Volusia County, a distance of nearly 6.7 miles. The project calls for resurfacing the travel and auxiliary lanes, paved shoulders and median crossovers.  Drainage improvements, guardrail replacement, and sidewalk reconstruction in certain locations is also included.

Contact Information
Communications Team
Britney Jones
(386) 740-3566
Britney.Jones@dot.state.fl.us
Contractor
Masci General Contractor, Inc.