Project Details
Work Type: Construction Work
Phase: Completed
Length: .250 miles
City:
County:
Road:
Construction Cost: $293,874
Project Start: Spring 2020
Est. Completion: Spring 2020
About
The work on this project includes concrete repair. joint rehabilitation, and applying  bridge deck epoxy overlay to the bridge deck to the S.R. 44 Bridge (Lytle Avenue) over U.S. 1 (S.R. 5).
Contact Information
Communications Team
Britney Jones
(386) 740-3566
Britney.Jones@dot.state.fl.us