Project Details
Work Type: Construction Work
Phase: Completed
City:
County:
Road:
Construction Cost: $332,500
Project Start: Summer 2017
Est. Completion: Late 2017
About

The improvements under this contract consist of fender system restoration below non-moveable bridges related to damage caused by Hurricane Matthew. Missing or damaged boards and wales on the fender system will be replaced. The fender system is similar to highway guardrails and protects the bridge piers from boats traveling through the channel.

Contact Information
Contractor
Seacoast, Inc.