Project Details
Work Type: Construction Work
Phase: Completed
City:
County:
Road:
Construction Cost: $3.17 Million
Project Start: Summer 2018
Est. Completion: Spring 2019
About
Work for this project includes cleaning and painting (metallizing) the steel surfaces of the S.R. A1A/Dunlawton Avenue bridge over the Halifax River (Bridge 790148). The project also includes cleaning and painting the steel bearings on piers 7,8,9 and 10.
Contact Information
Communications Team
Carolyn Fitzwilliam
(386) 943-5215
Carolyn.Fitzwilliam@dot.state.fl.us
Contractor
Intech Contracting LLC
Project Files